Filey Junior School

Client

Align Property Services (North Yorkshire County Council)

Main Contractor

William Birch & Sons Ltd

Contract Value

£ 100,000

The Project

The Filey Junior School Project commenced in the summer of 2018 and it consisted of replacing the three existing temporary classroom units with a newly built three classroom extension allowing students and staff a more permanent learning space with improved facilities. Due to the nature of this project it was time and operational sensitive for the school; the majority of it was still up and running throughout term time.

Filey Junior School

Playing Our Part

EMCE was awarded the full M&E package for this project. The services included:

  • New Boilers and Plant.
  • New Heating & Hot/Cold water services.
  • New radiators and sanitary ware.
  • Above ground drainage services.
  • Ventilation.
  • Sub distribution.
  • New lighting and emergency lighting.
  • New small power services.
  • Fire alarm.
  • TV distribution.
  • Security and access control systems.

The project was successfully completed within the time frame and to budget.

Since completion of the works; EMCE has continued to provide improvement works to other areas of the school